Warrior Square

Warrior Square, Hyde Housing Association

Richard Barwick project sheet (as a subcontractor to Hyde Housing Group). Coombs and Partners were not directly involved. Please see below.

Warrior Square development

Key parties

Hyde Housing Group; Osborne Property Services Ltd; RJ Barwick Ltd

Description

The building suffered major fire and water damage which led to the emergency evacuation and long-term displacement of residents, many of whom were elderly, infirm and vulnerable.

Three phases of reinstatement work, lasting over three years at a cost of circa £15m. Selected specialist contractors and consultant advisors were involved including RJ Barwick the appointed Hyde Group Project Manager for the duration, as well as supporting several major multi-party insurance claims.

Year – 2016

Primary risks

  1. Delays in reaching a successful outcome with insurers
  2. Counter claims from third parties (commercial tenants)
  3. Suitable long-term accommodation for displaced residents
  4. Structural stability and sustainable options for reinstatement